By Phil Marsh
THE Chinnor & Princes Risborough Railway has completed its new locomotive and stock servicing pit – making the heritage line an even more attractive destination for main line charters.
The lack of this vital piece of infrastructure was identified as a top priority after the railway’s main line connection was commissioned 18 months ago and despite a last minute snag, was made available in December.
Enjoy more Heritage Railway reading in the four-weekly magazine.
Click here to subscribe & save.
The 17-metre pit at Chinnor represents a substantial investment by the railway and follows the opening of its main line interchange station at Princes Risborough on August 15, as reported in issue 245.
A two-month delay in completing the pit was caused by the discovery of high-voltage power cables near the pit, after official plans had shown there were none.
Read more in Issue 250 of HR – on sale now!
Advert
Enjoy more Heritage Railway reading in the four-weekly magazine. Click here to subscribe.